Water Resource Management & Environmental Compliance

martin-martz-29PaIGCEq10-unsplash.jpg

Case Study

Sitewide Water Management Overhaul at Gulf Coast Mineral Facility

Challenge

Excess stormwater caused seasonal violations of discharge limits. Site also experienced drought-induced water shortages impacting wash plant operations.

ENG Solution

ENG Resources deployed a total site water management plan. This included automated decanting systems to preemptively release excess stormwater within permitted thresholds, reservoir planning for dry season reuse, and the integration of inline turbidity and pH sensors. Real-time data was linked to a remote dashboard monitored by both ENG and the client.

Results

  • 98% compliance rate over 18 monitored months

  • Reduced freshwater drawdown by 42%

  • $160,000 saved annually through reuse strategy

  • Passed state EPA audit with zero violations